Manwath, Parbhani

Industrial rooftop solar project

Ginning

150 kW

2.10 million kWh

INR 16.80 Lakhs
Sant Bhagatram Ginning is one of the oldest and most advanced cotton processing units in Manwath, Parbhani.
Sant Bhagatram Ginning aimed to offset its monthly electricity bills through net metering during the peak ginning season. The facility had sufficient rooftop space to install a 150 kW solar power system that could support high seasonal energy demand.
At the time of project execution, the ginning unit was operating at peak load. The owner required that solar installation activities be carried out without disturbing daily operations or causing any safety risks or downtime.
The project was carefully planned and executed while the plant remained fully operational. Infisol Energy completed the installation within just 40 days, meeting all safety and operational requirements and delivering the project to the complete satisfaction of the client.