Infisol Energy

Arihant Fibers

Airhant Fibers is a cotton fibre processing industry based in Parbhani.

Need

Along with its existing ginning operations, the addition of a new oil manufacturing unit significantly increased overall power consumption. To meet this rising demand and reduce dependency on grid power, the company decided to adopt solar energy.

 

Challenges

To avail depreciation benefits within the same financial year, the client set a strict and time-bound execution deadline for the solar project.

 

Solution

The Infisol Energy team planned and executed the 250 kW solar project efficiently and completed it within 45 days, well ahead of the committed timeline, enabling the client to achieve timely financial and operational benefits.